Suite 3B equipment schedule
CMP-26-101 active conflictBatches, CIP/SIP windows and equipment availability across the upstream and harvest skids. Built from the Maximo PM schedule and the MES planning extract; SAP ERP is not connected.
PM-204 sanitization overlaps MES-26074 inoculation by 4.5 h
Click any bar for details. Previews are local to this browser; the schedule of record in MES/Maximo is unchanged.
Constraint resolver sandbox
Two drafted options. Select one to preview it above. Neither is applied; a proposal needs supervisor and QA review.
Scenario A
Shift MES-26074 inoculation +4.5 h
- ConflictCalculated
Removed · inoculation starts after PM-SAN-204 ends (Mon 26 Oct 14:00)
- MES-26074 timelineCalculated
All downstream steps +4.5 h; harvest moves to Mon 9 Nov 14:00
- Media hold in vesselUnknown
25.5 h → 30.0 h. Validated hold limit not found in connected sources
- StaffingObservation
Inoculation lands at shift handover (14:00); supervisor confirmation needed
- QualificationObservation
No equipment substitution; no qualification impact
Scenario B
Divert MES-26074 feed to standby PM-205
- ConflictCalculated
Removed · MES-26074 uses PM-205; inoculation time unchanged
- QualificationObservation
PM-205 OQ overdue by 17 d · requires OQ re-execution or QA-approved justification
- PreparationCalculated
Tubing install + dynamic slip verification (SOP-UP-014 §7.2) ≈ 6 h before inoculation
- Batch recordObservation
Equipment substitution in eBR needs QA approval before execution
- Pump historyUnknown
PM-205 has no feed-delivery history on this process
Scenario A has fewer qualification dependencies; Scenario B keeps the timeline. The trade-off is a supervisor and QA decision.
Submit shift proposalEquipment availability
Next 7 days
| BR-UP-01 | Booked | MES-26073 → MES-26074 |
| PM-204 | Conflict | Sanitization vs inoculation |
| PM-205 | Not ready | OQ overdue · no tubing |
| CE-01 | Available | After Fri 23 08:00 |
| UF-DF-02 | Available | After Sat 24 02:00 |
| CIP skid | Available | 4 bookings, no overlap |
Data coverage
ObservationPM and CIP windows from Maximo.
UnknownOperator rosters and SAP ERP material availability are not connected, so staffing and material constraints are not checked.
Inspect affected pump PM-204Your companion
Here with you in BioDemo