Skip to content

Tech transfer portfolio

4 active projects

Projects moving processes between Mesa, Durham and Basel. Gate status reflects the transfer team’s stage-gate records; this view assembles them and flags blockers.

Gate records from DocumentumDemo · read-only
Frame TRANSFER-01

Published fermentation transfer projects

Change assumptions, run the model, or request an agent assessment

Loading source-grounded projects…

Active projects

4

Blocked gates

1

TT-006 Gate 2

At risk

1

TT-005 method transfer

Gate reviews next 14 d

2

TT-004 G3 · TT-003 G4

Project ledger

Gates: G0 Feasibility → G1 Process & analytics → G2 Engineering & CPP dossier → G3 Engineering run → G4 PPQ readiness

ProjectRouteGates 0–4CurrentNext milestoneLeadStatus
TT-006AB-mAb-014Mesa 500L single-use→ Durham 2000L stainless
  1. G0 Feasibility: cleared
  2. G1 Process & analytics: cleared
  3. G2 Engineering & CPP dossier: blocked
  4. G3 Engineering run: not started
  5. G4 PPQ readiness: not started
Gate 2 · blockedPID constants from Durham Automation · due 2026-11-06Alex RiveraGate 2 blocker
TT-004AB-mAb-009Mesa 2000L stainless→ Basel 2000L single-use
  1. G0 Feasibility: cleared
  2. G1 Process & analytics: cleared
  3. G2 Engineering & CPP dossier: cleared
  4. G3 Engineering run: in progress
  5. G4 PPQ readiness: not started
Gate 3 · engineering runEngineering run ER-04 starts 2026-11-02S. HoffmannOn plan
TT-005AB-bsAb-021Durham 200L single-use→ Mesa 500L single-use
  1. G0 Feasibility: cleared
  2. G1 Process & analytics: in progress
  3. G2 Engineering & CPP dossier: not started
  4. G3 Engineering run: not started
  5. G4 PPQ readiness: not started
Gate 1 · analytics transferMethod transfer protocol MTP-021 approvalK. OseiAt risk
TT-003AB-mAb-007Mesa downstream (UF-DF-02)→ Durham downstream
  1. G0 Feasibility: cleared
  2. G1 Process & analytics: cleared
  3. G2 Engineering & CPP dossier: cleared
  4. G3 Engineering run: cleared
  5. G4 PPQ readiness: in progress
Gate 4 · PPQ readinessPPQ protocol QA reviewD. KimOn plan

No readiness percentages are shown: gate clearance is a QA/MSAT decision recorded in the stage-gate system. Only TT-006 has a comparative workspace in this demo.

Cross-site equipment equivalency · TT-006

Mesa 500L single-use vs Durham 2000L stainless. Values from equipment specifications; blanks are shown as unknown, not estimated.

AspectMesa 500L SUB (donor)Durham 2000L stainless (recipient)ComparabilityClaim
Aspect ratio (H/D)1.5 : 12.0 : 1ScaledObservation
Impeller type1 × pitched-blade 45°, D/T 0.33Rushton (lower) + pitched-blade (upper), D/T 0.35GapObservation
SpargerDrilled-hole 1 mm + open pipeRing sparger 2 mmGapObservation
Power per volume (P/V)42.8 W/m³ (measured)Unknown · not characterisedUnknownUnknown
kLa (air, 0.05 vvm)8.4 h⁻¹Unknown · ENG-RPT-0447 not issuedUnknownUnknown
Control systemDeltaV v14 · gravimetric feed cascadeDeltaV v13 · flow-only feed loopGapObservation
Sources: Durham spec is Rev 1 (2023) and may be stale.