Mesa 500L single-use → Durham 2000L stainless
TT-006Gate 2 blockerAB-mAb-014 upstream transfer. Gate 2 Clearance (Engineering & CPP Dossier). Side-by-side comparison of donor and recipient equipment, with gaps and unknowns shown explicitly.
- G0 Feasibility: cleared
- G1 Process & analytics: cleared
- G2 Engineering & CPP dossier: blocked
- G3 Engineering run: not started
- G4 PPQ readiness: not started
Scale factor
Calculated1:4.00
2000 L / 500 L working volume
Volumetric power (donor)
Observation42.8W/m³
Recipient not measured
Unresolved blocker
Durham PID cascade tuning constants unmapped
Owner K. Osei · due 2026-11-06
Donor · Mesa 500L single-use
EQ-SPEC-MESA-SUB500 Rev 3
Recipient · Durham 2000L stainless
EQ-SPEC-DUR-SS2000 Rev 1 (2023 · may be stale)
Schematics are simplified and drawn to relative vessel scale only. Orange line = feed path; dashed red controller = unmapped loop.
Parameter comparability
Status per parameter. Unknowns stay unknown until a source supplies them.
| Parameter | Mesa 500L | Durham 2000L | Status | Note |
|---|---|---|---|---|
| Working volume | 500 L | 2000 L | ScaledCalculated | Scale factor 1:4.00 |
| Aspect ratio H/D | 1.5 | 2.0 | GapObservation | Taller vessel: longer mixing time and higher hydrostatic head at sparger |
| Impeller | 1 × PBT 45°, D/T 0.33 | Rushton + PBT, D/T 0.35 | GapObservation | Different power number; Rushton adds radial shear |
| Tip speed | 1.38 m/s @ 160 rpm | Not set | UnknownUnknown | Depends on Durham agitation setpoint, not yet chosen |
| Power per volume P/V | 42.8 W/m³ (measured) | 42.8 W/m³ (design basis) | ScaledCalculated | Constant-P/V basis is a target; Durham value not measured |
| kLa (air) | 8.4 h⁻¹ | Unknown | UnknownUnknown | Characterisation report ENG-RPT-0447 not issued |
| Aeration (VVM) | 0.05 vvm | 0.05 vvm (planned) | MatchObservation | Same VVM; different sparger bubble size |
| Feed control loop | Gravimetric cascade (DeltaV v14) | Flow-only FIC-2201 (DeltaV v13) · PID constants unmapped | GapObservation | Gate 2 blocker |
Gate 2 readiness checklist
2 done · 2 in progress · 1 blocked · 3 not started
Process description & CPP list transferred
DoneAlex Rivera · MSAT
Analytical methods transferred (titer, VCD)
DoneK. Osei · QC Durham
Equipment equivalency assessment
In progressR. Chen · Engineering
Feed-loop PID cascade constants mapped (FIC-2201)
BlockedK. Osei · Durham Automation
kLa characterisation at 2000 L (ENG-RPT-0447)
Not startedDurham Engineering
Recipe translation RCP-AB014 → Durham DeltaV v13
Not startedAlex Rivera · MSAT
Transfer risk assessment (FMEA)
In progressD. Kim · QA
Gate 2 dossier QA review
Not startedPriya Natarajan · QA
No readiness score is computed. Gate clearance is decided by the Gate 2 review board.